Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Which of the following are rational numbers
The opium trade resulted in conflict between _____. - Great Britain and Japan - Japan and China - Great Britain and China
which of them are functions of atomospher
How many 6-digit numbers are there in our system of counting numbers?
Listen to Beethoven’s Piano Sonata No. 14 (Adagio Sostenuto , Allegretto , Presto Agitato), also known as the Moonlight Sonata. There are three movements in thi
Jose receives a $10 gift card for downloading music and wants to determine how many songs he can purchase. Each downloaded song costs $1.19. Write and solve an
Find the circumference.Use 3.14 for TTr = 6 ft C = [?] ft NO BOTS
given f(x) = X^2 – 5x + 6 state a= b= c= min or max and y intercept
which organisms have the most amount of energy in the food web
Need help in one and four please