If 24 electricians can wire some new houses in 15 days, how many electricians would be required to do the job in 12 days?.

Respuesta :

shishirshrestha989
shishirshrestha989 shishirshrestha989
  • 04-01-2022

Answer:

here,

electrician/days

24 - 15

x(let). -12

direct proportion,

then,

exchange X up 24 down

or,24*15=12*X

or,24*15divided by 12=X

X=30

hence,30 electrician required to do complete in 12 days

Answer Link

Otras preguntas

How does the U.S. Constitution reflect the principle of democracy? It creates a republic government, which is the same as democracy. Most of the people can elec
Describe how the ocean plays a role in stabilizing Earth’s weather conditions
what physical property makes metal pots good for cooking?
how do I find the calculated sum of 1/7 and 1/2
33 is 33% of what number?
why would genetic material need to be able to reproduce
Madagascar (Lesson 06.01) •Which one of the following different creepy crawlers would you likely not discover when exploring the Madagascan forest? – giant hi
3/8 divided by 1/2 =
Woodrow Wilson believed that nations should be able to govern themselves. Which of the following Fourteen Points best reflects this belief? (Points : 2) I. "Ope
Which biome is characterized by low annual rainfall, less than 26 centimeters (about 10-11 inches) per year?